RED BAY | A recent audit of the Red Bay Water & Gas Board shows the utility system is on solid financial footing, while ongoing projects aim to expand service and strengthen long-term water capacity.
Board member Jason Vinson said an independent audit conducted by Sparks CPA firm delivered a “clean bill of health,” with financial indicators trending in a positive direction.
“The audit showed everything is moving the right way – income, expenses and bond ratings are all where they need to be,” Vinson said.
The audit covered the fiscal period ending Sept. 30, 2025. According to Vinson, the system’s bond ratings remain strong, with sufficient operating reserves on hand, a key factor in maintaining favorable bond ratings. He also noted the department secured nearly $800,000 in grant funding during the period, helping offset costs and improve overall financial performance.
While finances are stable, the board is also focused on making previously completed infrastructure begin generating returns.
One of those efforts involves expanding natural gas service in the Halltown area, where millions of dollars had already been invested in infrastructure but had not yet produced revenue.
“About $4 million had already been spent out there, but there were no customers connected because of how the project was originally done,” Vinson said.
To address that, the board approved an additional investment of roughly $100,000 to enable service connections for an estimated 100 to 120 customers.
“We looked at it as a separate investment,” Vinson said. “The $4 million is already spent. This gives us a chance to at least start generating some return and get service to those residents.”
Work is underway to complete connections, with a projected timeline of about six months from the start of construction. Some delays occurred due to permitting requirements, but officials expect customers to begin coming online by late summer or early fall.
Areas currently available for natural gas service include Strickland Road, Highway 124, Highway 25 north of Highway 24, Highway 23 north of Highway 24, Page Lane and Ledbetter Road. Residents in those areas can contact the utility office at 256-356-8622 for more information.
In addition to expanding service, the board is also exploring ways to increase water supply capacity for the future.
A key part of that plan involves the potential reopening of the Cooper Springs well, a water source that has not been used since the late early 2000s.
Vinson said preliminary testing has already been conducted to determine potential output, measured in gallons per minute. The board is also considering additional drilling in the area to assess whether more capacity could be developed.
The well was originally abandoned after the construction of a newer filtration plant, but officials now see value in restoring it as a secondary source.
“We’re trying to stay ahead,” Vinson said. “You see places run into problems with water loss or supply issues. We want to make sure we’re not in that situation.”
Reactivating Cooper Springs would provide redundancy for the system – essentially creating a backup supply – while helping meet the needs of existing customers and supporting industrial growth in the area. The project is still in its early stages, with the board currently pursuing grants and other funding sources to minimize costs to its customers.
“Our goal is to explore every avenue we can to get it back online without putting unnecessary burden on ratepayers,” Vinson said.